A bill of materials is the list of every component, sub-assembly and raw material, with the quantity and unit of each, needed to make one stated quantity of a finished or semi-finished item.

Why it exists: Because making something is a recipe problem before it is a stock problem: someone has to say what goes in, and in what quantity, before material can be bought, reserved, issued or costed.

Where it sits

  1. Bill of MaterialsThis document

Plan to produce: Bill of Materials → Work Order

Try it

What a production run needs from the store

Set the number of units. The table adds the raw materials of every level; a stocked sub-assembly stays one line.

A whole number, from 1 to 10,000.

Sample data, invented for this page. It is not a record from any system.

Raw materials for 100 units

Total raw materials. Equal parts from every level are added together.
ItemNeededTaken from
Copper winding (sample)40 kgMotor assembly (sample)
Rotor (sample)100 pcsMotor assembly (sample)
Bearing (sample)200 pcsMotor assembly (sample)
Base casting (sample)100 pcsStand assembly (sample)
Pole tube (sample)100 pcsStand assembly (sample)
M4 screw (sample)1,200 pcsStand assembly (sample), Table fan (sample)
Blade (sample)300 pcsTable fan (sample)
Carton (sample)100 pcsTable fan (sample)

How a bill of materials moves through its life

Four states. Pick one to see what a bill of materials is, and what it can still become.

Components and quantities are being set. A work order cannot use it.

Then: Active

Bill of Materials1 of 4
Bill of MaterialsDraft

Components and quantities are being set. A work order cannot use it.

Then: Active

Submitted and switched on. Work orders can use it, and one active BOM per item can be the default.

Then: Inactive

Bill of Materials2 of 4
Bill of MaterialsActive

Submitted and switched on. Work orders can use it, and one active BOM per item can be the default.

Then: Inactive

Switched off but kept, so history stays readable. New work orders cannot pick it, and it cannot be switched off while another active BOM uses it as a sub-assembly.

Then: Cancelled

Bill of Materials3 of 4
Bill of MaterialsInactive

Switched off but kept, so history stays readable. New work orders cannot pick it, and it cannot be switched off while another active BOM uses it as a sub-assembly.

Then: Cancelled

Withdrawn. It is switched off and no longer the default. A corrected copy replaces it.

Ends here

Bill of Materials4 of 4
Bill of MaterialsCancelled

Withdrawn. It is switched off and no longer the default. A corrected copy replaces it.

Ends here

Rules that must hold, and what breaks them

Rules

  • A bill of materials describes how to make one stated quantity of one item. Component quantities scale with the quantity ordered, so the quantity on the BOM is part of the recipe.
  • A BOM cannot contain its own finished item, directly or through a sub-assembly. The structure is a tree, and a loop would make the explosion endless.
  • Only an approved, active BOM can drive production, and a changed recipe is a new version. The BOM that earlier orders were made from is not edited to match the new one.

Does this happen in your business?

Tick what you recognise. Each tick shows what it costs.

Mistakes people make with bills of materials

Tick any that happen here.

In ERPNext, and in your system

How ERPNext models it

DocTypeWhat it does here
BOMSubmittable. item, quantity (the output quantity), items (components), with_operations, is_active, is_default. Most fields lock on submit. is_active, is_default and the rate-source settings stay editable. Version 16 renames the scrap table Secondary Items and adds phantom BOMs.
BOM ItemOne row per component: item_code, qty, uom, conversion_factor, source_warehouse, bom_no (the sub-assembly's own BOM) and do_not_explode.
BOM Explosion ItemThe flat list of raw materials across all levels, rebuilt on save. Each sub-assembly's own list is scaled by the quantity needed, and equal items are added together.
BOM Update ToolRuns Replace BOM and Update Cost as logged background jobs (BOM Update Log): swap one BOM for another wherever it is used, or refresh the cost of every BOM.

What other systems call it

SystemNameNote
ERPNextBOM (Bill of Materials)DocType BOM.
TallyBill of Materials (Set Components (BOM))Set on the stock item (Set Components (BOM) = Yes), with a BOM name such as Standard. An item can have several BoMs. The BoM is for items made in-house, not for trading items.
Zoho BooksComposite Items (Assembly type)Zoho Inventory has no separate bill-of-materials record: an assembly composite item lists its components. Also in Zoho Books through the Zoho Inventory add-on.
SAP Business OneBill of MaterialsProduction > Bill of Materials; multi-level, built one level at a time. Types: Production, Sales, Assembly and Template.
OdooBill of Materials (BoM)Manufacturing app. Multilevel BoMs have their own page in the same documentation.

From each maker's own documentation, checked 13 October 2026. A dash: not confirmed.

Where a bill of materials connects

Questions about bills of materials

The one most people ask is answered first. Type to find the rest.

What does a bill of materials mean for the business?

The bill of materials is the single source for what a product needs. Purchasing plans from it, the store issues against it, and the cost of the product is built from it. When the BOM is right, shortages show before the job starts. When it is wrong, every downstream number is wrong in the same direction.