Work Order

A work order is the document that authorises a manufacturer to produce a stated quantity of an item from a named bill of materials, and records the material consumed and the goods produced against that authorisation.

Why it exists: Because a recipe says how to make something, and someone still has to decide to make a certain quantity, now, from certain stock, and to show afterwards what it cost.

See it live

Where it sits

  1. Work OrderThis document

Plan to produce: Bill of Materials → Work Order

How a work order moves through its life

Seven states. Pick one to see what a work order is, and what it can still become.

Item, quantity and BOM are being set. Nothing is planned or reserved, and warehouses can still be blank.

Then: Not Started

Work Order1 of 7
Work OrderDraft

Item, quantity and BOM are being set. Nothing is planned or reserved, and warehouses can still be blank.

Then: Not Started

Submitted. The order adds planned quantity for the finished item and reserves raw materials for production. Warehouses are now required. No material has moved yet.

Then: In Process

Work Order2 of 7
Work OrderNot Started

Submitted. The order adds planned quantity for the finished item and reserves raw materials for production. Warehouses are now required. No material has moved yet.

Then: In Process

Material has been transferred to the work-in-progress warehouse, some output has been booked, or an operation has started. The order is live on the floor.

Then: Completed

Work Order3 of 7
Work OrderIn Process

Material has been transferred to the work-in-progress warehouse, some output has been booked, or an operation has started. The order is live on the floor.

Then: Completed

Produced quantity plus process loss has reached the quantity ordered. Finished goods are in the target warehouse, and the order no longer counts as planned or reserved.

Then: Stopped

Work Order4 of 7
Work OrderCompleted

Produced quantity plus process loss has reached the quantity ordered. Finished goods are in the target warehouse, and the order no longer counts as planned or reserved.

Then: Stopped

A manual hold on a submitted order that is not finished, off the main path. Unstopping resumes it, and a stopped order cannot be cancelled until it is unstopped.

Then: Closed

Work Order5 of 7
Work OrderStopped

A manual hold on a submitted order that is not finished, off the main path. Unstopping resumes it, and a stopped order cannot be cancelled until it is unstopped.

Then: Closed

A manual close that ends the order even when less was made than ordered. A closed order cannot be stopped or reopened.

Then: Cancelled

Work Order6 of 7
Work OrderClosed

A manual close that ends the order even when less was made than ordered. A closed order cannot be stopped or reopened.

Then: Cancelled

Reversed before any stock moved. An order cannot be cancelled while a submitted stock entry exists against it.

Ends here

Work Order7 of 7
Work OrderCancelled

Reversed before any stock moved. An order cannot be cancelled while a submitted stock entry exists against it.

Ends here

Rules that must hold, and what breaks them

Rules

  • A work order is for one item, one quantity and one active bill of materials. Nothing is made or consumed against it outside that quantity except within a stated tolerance.
  • Material reaches the order through documents. Transfers, consumption and finished goods are stock entries linked to the order, so what was issued, what was made and what is still in production can be read from the order.
  • An order that has moved stock cannot simply be cancelled. The stock entries against it are reversed first, and unfinished work is parked by stopping or closing the order.

Does this happen in your business?

Tick what you recognise. Each tick shows what it costs.

Mistakes people make with work orders

Tick any that happen here.

In ERPNext, and in your system

How ERPNext models it

DocTypeWhat it does here
Work OrderSubmittable. production_item, bom_no, qty, wip_warehouse, fg_warehouse, source_warehouse, produced_qty, process_loss_qty. The read-only status is worked out from the stock entries and operations against it. Version 16 adds Stock Reserved and Stock Partially Reserved.
Stock EntryThe documents that move material for the order, linked by work_order: Material Transfer for Manufacture (to the work-in-progress warehouse), Material Consumption for Manufacture, Manufacture (raw material out, finished goods in) and Disassemble.
Job CardCreated as drafts on submit when the BOM has operations: one per operation, recording workstation, time and completed quantity. It is the shop-floor record under the work order.
Manufacturing SettingsSets the overproduction allowance for work orders, whether raw material is backflushed from the BOM or from what was actually transferred, and whether serial and batch numbers are created from the work order.

What other systems call it

SystemNameNote
ERPNextWork OrderDocType Work Order.
Tally—No in-house work order or production order found in TallyPrime help. Production is recorded after the fact as a Manufacturing Journal (a mode of the Stock Journal voucher). Job work sent out is recorded with Job Work Out orders, and the job worker uses Job Work In.
Zoho Books—not verified as a document: Zoho Inventory's knowledge base says manufacturing modules are not supported yet and offers composite-item assemblies as a workaround (page undated, read 2026-10-13). An assembly puts components together to raise the stock of a composite item.
SAP Business OneProduction OrderOpens as Planned, then Released, then Closed. SAP's older Work Order was replaced by the Production Order from release 2005.
OdooManufacturing Order (MO)In Odoo a work order is one operation of an MO at a work center, not the whole order.

From each maker's own documentation, checked 13 October 2026. A dash: not confirmed.

Where a work order connects

Questions about work orders

The one most people ask is answered first. Type to find the rest.

What does a work order mean for the business?

The work order is where the plan becomes money. It reserves material, tracks work in progress and, when it closes, gives the cost of what was made. Planning reads open orders to see what is coming, the store reads them to know what to issue, and finance reads them to value work in progress.

Reviewed 14 October 2026. All 40 documents: the ERP glossary.